Sole Parent Support : Contents
Self-imposed stand-down
Where a client knows they will have a stand-down and delays their application for Sole Parent Support, the commencement date depends on whether the client has applied within 28 days of their entitlement date.
If the application is received within 28 days of the client's entitlement date, the commencement date will be:
- the day after initial stand-down ends
If the application is received 28 days after the client's entitlement date, the commencement date will be:
- the day after initial stand-down ends or
- the application date
whichever is the later.
Legislation
- stand down or stand-down period (definition) schedule 2 Social Security Act 2018
- Commencement of benefits section 311 Social Security Act 2018
- Benefits subject to stand down section 313 Social Security Act 2018
- Start and calculation of stand-down period section 316 Social Security Act 2018