Recompliance (13 week non-entitlement period)
A client or their partner can complete certain activities to get a temporary provisional benefit if they have a 13 week non-entitlement period because they:
- left a job voluntarily
- lost a job through misconduct
- have a grade 3 sanction imposed or
- refused an offer of suitable employment
If a client or partner wants to recomply, MSD must make a 6 week approved activity or programme of activities available to them at the earliest opportunity.
An approved activity can start as soon as a sanction has been imposed, there is no waiting period.
Recompliance activities
The client or partner their must do the approved activity for 6 continuous weeks, or until their 13 week non-entitlement period ends (whichever is earlier). This can be through:
- satisfactory participation in a 6 week approved activity or programme of activities
- satisfactory participation in full-time employment or
- part-time employment (if they have part-time work obligations)
Note clients and partners with full-time work obligations should have a full-time 6 week approved activity. Clients and partners with part-time work obligations should have a part-time 6-week approved activity.
Clients and partners with full-time work obligations who are recomplying through approved full-time employment do not get a provisional benefit.
Client does not complete activity
If a client fails to satisfactorily complete their 6-week activity or programme of activities , and their obligations have not changed, their provisional benefit must be reduced or stopped from the date it was increased or granted.
Any provisional benefit the client was paid must be established as a debt. To get a new benefit, the client must wait until the end of the 13-week non-entitlement period to re-apply or to get their full rate of benefit reinstated if the client has dependent children.
When a client with dependent children makes contact at the end of the 13 weeks, MSD should review their circumstances to confirm that the client still qualifies and what rate of payment they should get. MSD must determine the appropriate date to increase the rate from, but this cannot be any earlier than the end of the 13-week period.
Only one approved activity or programme can be assigned to a client. MSD cannot give the client a different approved activity if they fail to satisfactorily complete the original approved activity.
Recompliance for social obligations
If the client or their partner fails their obligations for a third time, and the third failure is a social obligation failure, then their 6 week recompliance activity MSD will be different.
In this situation it may not be appropriate to choose and activity focused on work outcomes. A programme of short-term approved activities may be more appropriate instead.
For more information see:
Approved activity examples
Here are some examples that may be a suitable 6-week approved activity for the client or partner:
Note this list is an example only. An approved activity (or programme of suitable activities) should be relevant to the obligation the client failed, and be fair and reasonable.
Programme of suitable activities
If there is not an appropriate 6 week approved activity available, consider a programme of suitable activities.
For more information see:
For when to grant or increase the benefit, see:
For what to do if a client or partner cannot recomply, see:
For more information see:
Legislation
- Effect of participation in certain activities on non-entitlement period section 324 Social Security Act 2018
- General obligation to be available for suitable employment, etc section 144 Social Security Act 2018
- Work-test obligations as required by MSD section 146 Social Security Act 2018
- Obligation to undertake and pass drug test section 147 Social Security Act 2018